BASIC ORDER OF CONSTRUCTION


With some variation, depending on jobsite and weather conditions, the following is a list of the basic order of construction:

  • Basement excavated (if applicable)
  • Trenching completed and footings poured
  • Basement stem-wall and floor poured (if applicable)
  • Backfill foundation - foundation and garage slab poured
  • Rough carpentry construction – framing of home
  • Utility installation (gas, electric, water/sewer laterals, septic or well)
  • Roofing materials and tile/shingle-type installed
  • Mechanical rough-in completed (heating, plumbing and electrical)
  • Siding installed
  • Insulation installed
  • Drywall installed, taped and textured
  • Millwork delivered - painting and staining begins
  • Finished carpentry – installation of wood flooring, stair railings, floor trim-board, cabinets, window and door trim, and all finish millwork
  • Underlayment installed at vinyl and ceramic tile areas
  • Countertops installed
  • Vinyl and ceramic tile installed
  • Built-in appliances installed
  • Lighting fixtures installed
  • Heating/cooling, plumbing and electrical completed
  • Remaining custom flooring and custom built-in’s installed
  • Appliances that are not built-in are delivered and installed
  • Finishing touches completed
  • Occupancy scheduled

    Once we arrive at the scheduling of occupancy, Amberwood Homes will conduct a thorough walk-through inspection with you to ensure that all of your expectations have been met, and everything specified in your construction contracts are included in the home. We will answer any questions you may have and show you how to operate all of your appliances, and then give you the keys to your new home. And, we hope we have met, and exceeded, your expectations, so you will recommend Amberwood Homes to your friends!


    OUR STEP BY STEP PROCESS

    1. INITIAL DESIGN & BUDGET MEETING
    2. DESIGN AGREEMENT
    3. REVIEW DETAILED DRAWINGS
    4. WORKING DRAWINGS & SPECIFICATIONS
    5. NEW HOME CONSTRUCTION CONTRACTS
    6. COMPLETE THE HOME LOAN PROCESS
    7. BUILDING PERMIT APPLICATION
    8. COMPLETE CUSTOMER SELECTIONS
    9. BASIC ORDER OF CONSTRUCTION



  • @ CUSTOMER SERVICE Copyright AMBERWOODHOMES.COM © All Rights Reserved